Do I need a permit to connect to the water system?

Starting & Connecting Service

Yes. You must get a Service Connection Permit ($95) from the utility before connecting to, repairing, modifying, decommissioning, or abandoning any water service connection.


You cannot connect to, repair, modify, decommission, or abandon utility service connections without first getting a connection permit from the utility.

Service Connection Permit Fee: $95 (Section W-027.15)

What you need to apply:

  • The permit fee ($95)
  • Your name, address, and phone number
  • Legal description of the property to be served
  • For private systems, multi-family buildings (more than 2 units), branched service extensions, or commercial structures: engineered plans stamped by a professional engineer registered in Alaska
  • Evidence of any required permits from other government agencies

Plan Review Fee: $190 (if engineered plans are required) - Section W-027.16

The utility will issue the permit if your application and proposed construction meet tariff requirements and applicable law.

Inspections are required: After you install the connection, it must be inspected and approved before you can backfill. See Permits & Inspections for more details.

Tariff Reference: Section W-020-A, Section W-027.15, Section W-027.16